UNIT DAMAGE HAZARD
Failure to follow this caution may result in damage to the heat
exchangers due to over temperature or condensate corrosion.
1. NEVER connect Low Speed (Red) wire to “HI HEAT”.
2. Do NOT connect Medium Low Speed (Blue) wire to
“HI-HEAT” on 80,000 Btuh and 120,000 Btuh input
model sizes.
CAUTION
!
Table 18 Speed Selection
LEAD COLOR SPEED AS SHIPPED
White Common COM
Black High Cool
Yellow M e d --- H i g h SPARE
Orange† Med H i g h --- G a s H e a t
Blue M e d --- L o w Spare/High---Gas Heat
Red Low* L o w --- G a s H e a t
* Continuous blower speed
Available on 5-speed blowers only
For low-heat, the following connections can be made at LO-
HEAT on control:
a. Med (Orange) -- Available only on 5-speed motors
b. Med-Low (Blue)
c. Low (RED) -- Factory setting.
To change blower motor speed selections for heating mode,
remove blower motor lead from control HI-HEAT terminal. (See
Fig. 37.) Select desired blower motor speed lead from one of the
other motor leads and relocate it to HI-HEAT terminal. See Table
18 for lead color identification. Reconnect original lead on
SPARE terminal. Follow this same procedure for proper selection
of LO-HEAT and COOL speed selection.
Set Blower Off Delay
a. Remove Blower Access Door if installed.
b.TurnDipswitch2and3ONorOFFfordesired
blower off delay. See Table 11 and 12 or Fig. 36
and 37.
ADJUST BLOWER OFF DELAY (HEAT MODE)
If desired, the main blower off time delay period may be
lengthened or shortened when operating in the heating mode to
provide greater comfort. See Table 11 for position of switches
and Fig. 36 or 37 for location of switches on control center.
SETTHERMOSTATHEATANTICIPATOR
When using a nonelectronic thermostat, the thermostat
heat-anticipator must be set to match the amp draw of
the electrical components in R-W/W1 circuit. Accurate amp
draw readings can be obtained at thermostat subbase terminals
RandW.
Fig. 61 illustrates an easy method of obtaining actual amp draw.
The amp reading should be taken after blower motor has started
and furnace is operating in low heat. To operate furnace in
low-heat, first move SW-1 to ON position, then connect ammeter
wires as shown in Fig. 61. The thermostat anticipator should
NOT be in the circuit while measuring current. If thermostat has
no subbase, the thermostat must be disconnected from R and
W/W1 wires during current measurement Return SW-1 to final
desired location after completing the reading.
See thermostat manufacturers instructions for adjusting heat
anticipator and for varying heating cycle length.
When using an electronic thermostat, set cycle rate for 3 cycles
per hour.
Step 6 -- Check Safety Controls
This section covers the safety controls that must be checked
before the installation is complete. The flame sensor, gas valve,
and pressure switch were all checked in the Start-up procedure
section as part of normal operation.
1. Check Primary Limit Control
This control shuts off gas control system and energizes
air-circulating blower motor if furnace overheats.
Recommended method of checking this limit control is to
gradually block off return air after furnace has been
operating for a period of at least 5 minutes. As soon as
limit control has shut off burners, return-air opening
should be unblocked to permit normal air circulation. By
using this method to check limit control, it can be
established that limit is functioning properly and operates
if there is a restricted return-air supply or motor failure. If
limit control does not function during this test, cause must
be determined and corrected.
R Y W G
10 TURNS
THERMOSTAT SUBBASE
TERMINALS WITH
THERMOSTAT REMOVED
HOOK-AROUND
VOLT/AMMETER
EXAMPLE:
5.0 AMPS ON AMMETER
10 TURNS AROUND JAWS
= 0.5 AMPS FOR THERMOSTAT SETTING
FROM UNIT 24-VOLT
TERMINAL BLOCK
A80201
Fig. 61 -- Amp Draw Check with Ammeter
2. Check Pressure Switch
This control proves operation of draft inducer. Check switch
operation as follows:
a. Turn off 115-v power to furnace.
b. Remove outer furnace door and disconnect inducer
motor lead wires from wire harness.
c. Turn on 115-v power to furnace.
d. Set thermostat to “call for heat” and wait 1 minute.
When pressure switch is functioning properly, hot
surface igniter should not glow, and status code LED
flashes a Status Code 32. If hot surface ignitor glows
when inducer motor is disconnected, shut furnace
down immediately. Determine reason pressure switch
did not function properly and correct condition.
e. Turn off 115-v power to furnace.
f. Reconnect inducer motor leads, reinstall main furnace
door, and turn on 115-v power supply.